Beta · built from public sources · records marked draft are not yet independently verified · How we grade evidence
// Record #7 — facility disclosure

Nebius at Ark Longcross Park: operational

Nov 2025 · United Kingdom

// Facts, as published
Facility status
operational
IT power (MW)
16
Power, as published
16MW
Power qualifier
exact
GPUs (as stated)
4,000
GPU model
NVIDIA HGX B300
// Curator note

June 2026: £807m expansion with new 36MW LP02 building reported.

// Parties
developer
Ark Data Centres GB
operator
Nebius NL
// Facilities
subject
Nebius at Ark Longcross Park Longcross GB
// Evidence
Archived primary
capture #1793 · 22 Oct 2026 · HTTP 200 · sha256 a290d0cb3f2601e7497724c719516365a394e3c71b4ea26fcd91d75407cd8aa7
// Version history
VersionStatusGradeRightsRecordedReason
v1draftCpending_review22 Oct 2026created